[xwiki-devs] New planning for XE 1.4 releases

Sergiu Dumitriu sergiu at xwiki.com
Wed Apr 2 14:12:31 CEST 2008


Vincent Massol wrote:
> On Apr 2, 2008, at 11:47 AM, Vincent Massol wrote:
> 
>> On Apr 2, 2008, at 11:27 AM, Jean-Vincent Drean wrote:
>>
>>> On Wed, Apr 2, 2008 at 11:20 AM, Jean-Vincent Drean <jv at xwiki.com>  
>>> wrote:
>>>> Hi,
>>>>
>>>> Since XWiki Enterprise 1.4M1 has been delayed by 1 week we have to
>>>> modify the planning a bit.
>>>> So here are the proposed dates:
>>>>
>>>> * XE 1.4 M1 - Tomorrow
>>>> * XE 1.4 M2 - April 3rd
>>>> * XE 1.4 RC1 - April 25
>>>> * XE 1.4 RC2 - May 8
>>>> * XE 1.4 Final - May 13
>>>>
>>> Oops, correction :
>>>
>>> * XE 1.4 M1 - Tomorrow
>>> * XE 1.4 M2 - April 24
>>> * XE 1.4 RC1 - May 5
>>> * XE 1.4 RC2 - May 12
>>> * XE 1.4 Final - May 16
>> -0
>>
>> I'd really like that we don't change the final release date and keep  
>> it as planned. It's not good practice to shift.
>> We should instead modify slightly the intermediary dates but keep  
>> the same final date.
>> Of course this means we'll have a little bit less content but that's  
>> not important. What's important is that we 1) release often and 2)  
>> keep the dates that we announce.
> 
> Before we finalize let's review what we want to include in 1.4M2:
> 
> 1) new xmlrpc improvements (Fabio)
> 2) improved stats performance (ThomasM)
> 3) Skins extensions (Sergiu)
> 4) some perf improvements (JV)
> 
> Imagine we decided to reduce the 1.4M2 release from 3 weeks to 2 weeks  
> in order to have the same final release date for 1.4. What can be done  
> in 1) through 4) within 2 weeks (10 days) starting today?
> 
> Thanks
> -Vincent

OK for 3.
-- 
Sergiu Dumitriu
http://purl.org/net/sergiu/


More information about the devs mailing list