I think that it's not nice to plan 1.0.1 so soon... It means that we already know there are bugs, and we're releasing a buggy product anyway.

Also, I don't know if we can count on a 1.1 release so soon. We currently lack the power to push things so fast. Remember, only you (Vincent) and Nam are going to work on the core in the next few weeks/months.

On 4/6/07, Vincent Massol <vincent@massol.net> wrote:
To be more precise here are some proposed dates:

- 1.0 RC1: 16/Apr/07
- 1.0 final: 23/Apr/07
- 1.0.1: 07/May/07
- 1.1 B1: 21/May/07
- 1.1 final: not defined

Please all committers answer on my previous email and this one to
ensure we're all on the same page and all agree on the way forward...

Thanks
-Vincent

On Apr 6, 2007, at 3:17 PM, Vincent Massol wrote:

> Hi,
>
> I'd like to propose the following:
>
> * Release RC1 by end of next week with as many important bugs fixed
> as possible
> * Wait for 1 week after RC1 is released and declare RC1 to be 1.0
> final is no critical/blocking bugs are found
> * Dedicate the XWIKI 1.0 branch to contain ONLY bug fixes going
> forward
> * Put new features/improvements ONLY on trunk
> * Release 1.0.1 2 to 3 weeks after 1.0 is released with bug fixes
> * Define a roadmap for 1.1 in term of what we want in it. It should
> be achievable within 3 months.
> * Change the version on trunk to be 1.1-beta-1 and release after
> 2-3 weeks. Increase to 1.1-beta-2 and repeat, etc. till we either
> reach something close so the initial roadmap for 1.1 in term of
> features or we reach the 3 months delay. In any case, release 1.1
> at that time.
> * I propose to NOT create a branch for 1.1 till the final 1.1 is
> released and when it is I propose we don't release 1.0.x releases
> any more and instead release 1.1.x bug fixes releases (we don't
> have enough manpower to support more than 2 releases in parallel,
> it's already going to stretch us a lot).
>
> WDYT?
>
> Thanks
> -Vincent