[xwiki-devs] [GSOC][WEBDAV] Status (Refactoring, Almost Done)
Hi Ludovic, Sorry about going ahead with refactoring instead of test cases but i thought it would be easier to write tests once the code is refactored. I've completed most of the refactoring but it will take about 2 more days to finish it off. Please have a look at the new code base if you have a time [ i know you are busy :) ] and let me know what you think. I hope following deadlines (swapped refactoring and test case writing) are ok with you, 21st - Finish Refactoring 28th - Finish Test Case Writing ... Rest is same Thanks a lot. - Asiri
Forgot to mention that i've choosed jakarta slide<http://jakarta.apache.org/slide/>for writing test cases. Slide is a retired project but i belive it has the most complete webdav client library up to date. - Asiri On Fri, Jul 18, 2008 at 7:25 AM, Asiri Rathnayake < [email protected]> wrote:
Hi Ludovic,
Sorry about going ahead with refactoring instead of test cases but i thought it would be easier to write tests once the code is refactored. I've completed most of the refactoring but it will take about 2 more days to finish it off.
Please have a look at the new code base if you have a time [ i know you are busy :) ] and let me know what you think.
I hope following deadlines (swapped refactoring and test case writing) are ok with you,
21st - Finish Refactoring 28th - Finish Test Case Writing
... Rest is same
Thanks a lot.
- Asiri
participants (1)
-
Asiri Rathnayake