Hi devs, One of the main goals of 4.2 release was to be able to upgrade an XWiki farm in a few minutes. Thomas has started working on this and I need to improve the UI which is currently very minimal. We are pretty late overall and one way to still have this in 4.2 is to postpone the final release by adding a third milestone. The current planning is: * 4.2M2: 6 Aug 2012 (Today!) * 4.2RC1: 20 Aug 2012 * 4.2Final: 27 Aug 2012 With a third milestone we could have this: * 4.2M2: 6 Aug 2012 (Today!) * 4.2M3: 27 Aug 2012 * 4.2RC1: 10 Sep 2012 * 4.2Final: 17 Sep 2012 However, doing this means we're going to miss the unofficial "1 cycle per year rule" (we were already over 1 year at the current rate but it's going to be worse with this) which means we would need from now on to have shorter release cycle for the 4.x cycle: * 4.3: October (2 months) * 4.4: December (1 month) * 4.5: January (1 month) In any case the 4.4 and 4.5 release are supposed to be cycle stabilization releases so it's not a bad thing. We just need to agree we're not going to put any more big stuff in the 4.x cycle. One thing we would still need to put in is a new skin which must go in 4.3 (would be too late afterwards). I'm +1. Thanks, Marius P.S.: This is actually Vincent's proposal, but I'm sending the vote myself because he's on holiday.
+1 On Mon, Aug 6, 2012 at 11:28 AM, Marius Dumitru Florea <[email protected]> wrote:
Hi devs,
One of the main goals of 4.2 release was to be able to upgrade an XWiki farm in a few minutes. Thomas has started working on this and I need to improve the UI which is currently very minimal. We are pretty late overall and one way to still have this in 4.2 is to postpone the final release by adding a third milestone.
The current planning is:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2RC1: 20 Aug 2012 * 4.2Final: 27 Aug 2012
With a third milestone we could have this:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2M3: 27 Aug 2012 * 4.2RC1: 10 Sep 2012 * 4.2Final: 17 Sep 2012
However, doing this means we're going to miss the unofficial "1 cycle per year rule" (we were already over 1 year at the current rate but it's going to be worse with this) which means we would need from now on to have shorter release cycle for the 4.x cycle:
* 4.3: October (2 months) * 4.4: December (1 month) * 4.5: January (1 month)
In any case the 4.4 and 4.5 release are supposed to be cycle stabilization releases so it's not a bad thing.
We just need to agree we're not going to put any more big stuff in the 4.x cycle. One thing we would still need to put in is a new skin which must go in 4.3 (would be too late afterwards).
I'm +1.
Thanks, Marius
P.S.: This is actually Vincent's proposal, but I'm sending the vote myself because he's on holiday. _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
-- Thomas Mortagne
On 08/06/2012 05:28 AM, Marius Dumitru Florea wrote:
Hi devs,
One of the main goals of 4.2 release was to be able to upgrade an XWiki farm in a few minutes. Thomas has started working on this and I need to improve the UI which is currently very minimal. We are pretty late overall and one way to still have this in 4.2 is to postpone the final release by adding a third milestone.
The current planning is:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2RC1: 20 Aug 2012 * 4.2Final: 27 Aug 2012
With a third milestone we could have this:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2M3: 27 Aug 2012 * 4.2RC1: 10 Sep 2012 * 4.2Final: 17 Sep 2012
+1.
However, doing this means we're going to miss the unofficial "1 cycle per year rule" (we were already over 1 year at the current rate but it's going to be worse with this) which means we would need from now on to have shorter release cycle for the 4.x cycle:
* 4.3: October (2 months) * 4.4: December (1 month) * 4.5: January (1 month)
In any case the 4.4 and 4.5 release are supposed to be cycle stabilization releases so it's not a bad thing.
+1 as well.
We just need to agree we're not going to put any more big stuff in the 4.x cycle. One thing we would still need to put in is a new skin which must go in 4.3 (would be too late afterwards).
I'm +1.
Thanks, Marius
P.S.: This is actually Vincent's proposal, but I'm sending the vote myself because he's on holiday.
-- Sergiu Dumitriu http://purl.org/net/sergiu/
+1 On Mon, Aug 6, 2012 at 6:39 PM, Sergiu Dumitriu <[email protected]> wrote:
On 08/06/2012 05:28 AM, Marius Dumitru Florea wrote:
Hi devs,
One of the main goals of 4.2 release was to be able to upgrade an XWiki farm in a few minutes. Thomas has started working on this and I need to improve the UI which is currently very minimal. We are pretty late overall and one way to still have this in 4.2 is to postpone the final release by adding a third milestone.
The current planning is:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2RC1: 20 Aug 2012 * 4.2Final: 27 Aug 2012
With a third milestone we could have this:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2M3: 27 Aug 2012 * 4.2RC1: 10 Sep 2012 * 4.2Final: 17 Sep 2012
+1.
However, doing this means we're going to miss the unofficial "1 cycle
per year rule" (we were already over 1 year at the current rate but it's going to be worse with this) which means we would need from now on to have shorter release cycle for the 4.x cycle:
* 4.3: October (2 months) * 4.4: December (1 month) * 4.5: January (1 month)
In any case the 4.4 and 4.5 release are supposed to be cycle stabilization releases so it's not a bad thing.
+1 as well.
We just need to agree we're not going to put any more big stuff in the
4.x cycle. One thing we would still need to put in is a new skin which must go in 4.3 (would be too late afterwards).
I'm +1.
Thanks, Marius
P.S.: This is actually Vincent's proposal, but I'm sending the vote myself because he's on holiday.
-- Sergiu Dumitriu http://purl.org/net/sergiu/
______________________________**_________________ devs mailing list [email protected] http://lists.xwiki.org/**mailman/listinfo/devs<http://lists.xwiki.org/mailman/listinfo/devs>
-- Denis Gervalle SOFTEC sa - CEO eGuilde sarl - CTO
+1 Thanks -Vincent PS: Thanks Marius for having handled this :) On Aug 6, 2012, at 11:28 AM, Marius Dumitru Florea wrote:
Hi devs,
One of the main goals of 4.2 release was to be able to upgrade an XWiki farm in a few minutes. Thomas has started working on this and I need to improve the UI which is currently very minimal. We are pretty late overall and one way to still have this in 4.2 is to postpone the final release by adding a third milestone.
The current planning is:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2RC1: 20 Aug 2012 * 4.2Final: 27 Aug 2012
With a third milestone we could have this:
* 4.2M2: 6 Aug 2012 (Today!) * 4.2M3: 27 Aug 2012 * 4.2RC1: 10 Sep 2012 * 4.2Final: 17 Sep 2012
However, doing this means we're going to miss the unofficial "1 cycle per year rule" (we were already over 1 year at the current rate but it's going to be worse with this) which means we would need from now on to have shorter release cycle for the 4.x cycle:
* 4.3: October (2 months) * 4.4: December (1 month) * 4.5: January (1 month)
In any case the 4.4 and 4.5 release are supposed to be cycle stabilization releases so it's not a bad thing.
We just need to agree we're not going to put any more big stuff in the 4.x cycle. One thing we would still need to put in is a new skin which must go in 4.3 (would be too late afterwards).
I'm +1.
Thanks, Marius
P.S.: This is actually Vincent's proposal, but I'm sending the vote myself because he's on holiday.
participants (5)
-
Denis Gervalle -
Marius Dumitru Florea -
Sergiu Dumitriu -
Thomas Mortagne -
Vincent Massol