Hi, Since we have failed the 2.2M1 release date I propose the following new schedule: Original dates: * 2.2M1: 28 Dec 2009 * 2.2M2: 18 Jan 2010 * 2.2RC1: 1st Feb 2010 * 2.2 RC2/Finale: 8 Feb 2010 New dates: * 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new profile UI + new watchlist UI and he may need one day more) * 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've almost done all planned stuff in 2.2M1 - see http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) * 2.2RC1: 1st Feb * 2.2 RC2/Finale: 8 Feb Here's my +1 Thanks -Vincent
+1 Thanks, Marius Vincent Massol wrote:
Hi,
Since we have failed the 2.2M1 release date I propose the following new schedule:
Original dates:
* 2.2M1: 28 Dec 2009 * 2.2M2: 18 Jan 2010 * 2.2RC1: 1st Feb 2010 * 2.2 RC2/Finale: 8 Feb 2010
New dates:
* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new profile UI + new watchlist UI and he may need one day more) * 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've almost done all planned stuff in 2.2M1 - see http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) * 2.2RC1: 1st Feb * 2.2 RC2/Finale: 8 Feb
Here's my +1
Thanks -Vincent _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
+1 On Thu, Jan 7, 2010 at 11:46, Vincent Massol <[email protected]> wrote:
Hi,
Since we have failed the 2.2M1 release date I propose the following new schedule:
Original dates:
* 2.2M1: 28 Dec 2009 * 2.2M2: 18 Jan 2010 * 2.2RC1: 1st Feb 2010 * 2.2 RC2/Finale: 8 Feb 2010
New dates:
* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new profile UI + new watchlist UI and he may need one day more) * 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've almost done all planned stuff in 2.2M1 - see http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) * 2.2RC1: 1st Feb * 2.2 RC2/Finale: 8 Feb
Here's my +1
Thanks -Vincent _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
-- Thomas Mortagne
On 01/07/2010 11:46 AM, Vincent Massol wrote:
Hi,
Since we have failed the 2.2M1 release date I propose the following new schedule:
Original dates:
* 2.2M1: 28 Dec 2009 * 2.2M2: 18 Jan 2010 * 2.2RC1: 1st Feb 2010 * 2.2 RC2/Finale: 8 Feb 2010
New dates:
* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new profile UI + new watchlist UI and he may need one day more) * 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've almost done all planned stuff in 2.2M1 - see http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) * 2.2RC1: 1st Feb * 2.2 RC2/Finale: 8 Feb
Here's my +1
Thanks -Vincent
+1 -- Sergiu Dumitriu http://purl.org/net/sergiu/
Hi,
Since we have failed the 2.2M1 release date I propose the following new schedule:
Original dates:
* 2.2M1: 28 Dec 2009 * 2.2M2: 18 Jan 2010 * 2.2RC1: 1st Feb 2010 * 2.2 RC2/Finale: 8 Feb 2010
New dates:
* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new profile UI + new watchlist UI and he may need one day more)
+1 FYI, I'm about to commit new Importer UI (likely this afternoon or tomorrow) Jerome.
* 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've almost done all planned stuff in 2.2M1 - see http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) * 2.2RC1: 1st Feb * 2.2 RC2/Finale: 8 Feb
Here's my +1
Thanks -Vincent _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
+1, JV. On Thu, Jan 7, 2010 at 11:46 AM, Vincent Massol <[email protected]> wrote:
Hi,
Since we have failed the 2.2M1 release date I propose the following new schedule:
Original dates:
* 2.2M1: 28 Dec 2009 * 2.2M2: 18 Jan 2010 * 2.2RC1: 1st Feb 2010 * 2.2 RC2/Finale: 8 Feb 2010
New dates:
* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new profile UI + new watchlist UI and he may need one day more) * 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've almost done all planned stuff in 2.2M1 - see http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) * 2.2RC1: 1st Feb * 2.2 RC2/Finale: 8 Feb
Here's my +1
Thanks -Vincent _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
+1 Caleb Jean-Vincent Drean wrote:
+1,
JV.
On Thu, Jan 7, 2010 at 11:46 AM, Vincent Massol <[email protected]> wrote:
Hi,
Since we have failed the 2.2M1 release date I propose the following new schedule:
Original dates:
* 2.2M1: 28 Dec 2009 * 2.2M2: 18 Jan 2010 * 2.2RC1: 1st Feb 2010 * 2.2 RC2/Finale: 8 Feb 2010
New dates:
* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new profile UI + new watchlist UI and he may need one day more) * 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've almost done all planned stuff in 2.2M1 - see http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap) * 2.2RC1: 1st Feb * 2.2 RC2/Finale: 8 Feb
Here's my +1
Thanks -Vincent _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
_______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
participants (7)
-
Caleb James DeLisle -
Jean-Vincent Drean -
Jerome Velociter -
Marius Dumitru Florea -
Sergiu Dumitriu -
Thomas Mortagne -
Vincent Massol