[xwiki-devs] [VOTE] Postpone 4.2 final release date to 24th of September 2012
Hi devs, Current release dates for 4.2 are: - 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012 Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :( So I'd like to propose: - 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012 Here's my +1 Thanks -Vincent PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year.
+1 Thanks, Eduard On Wed, Sep 12, 2012 at 12:56 PM, Vincent Massol <[email protected]> wrote:
Hi devs,
Current release dates for 4.2 are:
- 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012
Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :(
So I'd like to propose:
- 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012
Here's my +1
Thanks -Vincent
PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year. _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
+1 Thanks, Caty On Wed, Sep 12, 2012 at 1:06 PM, Eduard Moraru <[email protected]> wrote:
+1
Thanks, Eduard
On Wed, Sep 12, 2012 at 12:56 PM, Vincent Massol <[email protected]> wrote:
Hi devs,
Current release dates for 4.2 are:
- 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012
Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :(
So I'd like to propose:
- 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012
Here's my +1
Thanks -Vincent
PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year. _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
_______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
+1 On Wed, Sep 12, 2012 at 11:56 AM, Vincent Massol <[email protected]> wrote:
Hi devs,
Current release dates for 4.2 are:
- 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012
Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :(
So I'd like to propose:
- 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012
Here's my +1
Thanks -Vincent
PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year. _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
-- Jean-Vincent Drean, XWiki.
+1 On Wed, Sep 12, 2012 at 11:56 AM, Vincent Massol <[email protected]> wrote:
Hi devs,
Current release dates for 4.2 are:
- 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012
Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :(
So I'd like to propose:
- 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012
Here's my +1
Thanks -Vincent
PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year. _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
-- Thomas Mortagne
+1 Thanks, Marius On Wed, Sep 12, 2012 at 12:56 PM, Vincent Massol <[email protected]> wrote:
Hi devs,
Current release dates for 4.2 are:
- 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012
Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :(
So I'd like to propose:
- 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012
Here's my +1
Thanks -Vincent
PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year. _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
On 09/12/2012 05:56 AM, Vincent Massol wrote:
Hi devs,
Current release dates for 4.2 are:
- 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012
Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :(
So I'd like to propose:
- 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012
Here's my +1
Thanks -Vincent
PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year.
+1. -- Sergiu Dumitriu http://purl.org/net/sergiu/
+1 On Wed, Sep 12, 2012 at 5:21 PM, Sergiu Dumitriu <[email protected]> wrote:
On 09/12/2012 05:56 AM, Vincent Massol wrote:
Hi devs,
Current release dates for 4.2 are:
- 4.2M3: 3 sep 2012 - 4.2RC1: 10 Sep 2012 - 4.2Final: 17 Sep 2012
Since we're already the 12th of Sep (i.e. late by **9** days on M3) his is obviously not going to happen… :(
So I'd like to propose:
- 4.2M3: 12th Sep 2012 - 4.2RC1: 19th Sep 2012 - 4.2Final: 24th Sep 2012
Here's my +1
Thanks -Vincent
PS: I'd like not to postpone 4.2 final by more than 1 week because it means 4.3 will get shorter since we need to finish the 4.X cycle ASAP so that we can start the 5.x one as close as possible to the beginning of next year.
+1.
-- Sergiu Dumitriu http://purl.org/net/sergiu/
______________________________**_________________ devs mailing list [email protected] http://lists.xwiki.org/**mailman/listinfo/devs<http://lists.xwiki.org/mailman/listinfo/devs>
-- Denis Gervalle SOFTEC sa - CEO eGuilde sarl - CTO
participants (8)
-
Denis Gervalle -
Ecaterina Moraru (Valica) -
Eduard Moraru -
Jean-Vincent Drean -
Marius Dumitru Florea -
Sergiu Dumitriu -
Thomas Mortagne -
Vincent Massol