[xwiki-devs] [Release] Status of the release
Hi devs, The 3.3 Milestone 2 release was supposed to happen this past Monday, but the codebase hasn't been stable enough for a release (failing tests, hot commits triggering comments, unmerged branches). Proposal 1: Release 3.3 RC 1 next Monday, 21 November, effectively dropping Milestone 2. This respects the initial schedule, although some of the targeted features won't be fully usable. This means that everyone should try to get their code stabilized. Proposal 2: Lengthen the release by another week, releasing: - Milestone 2 next Monday, November 21 - RC1 on November 28 - Final on December 5 I'm fine with either one, if the codebase is stable enough for a RC by next Monday. -- Sergiu Dumitriu http://purl.org/net/sergiu/
On Thu, Nov 17, 2011 at 20:51, Sergiu Dumitriu <[email protected]> wrote:
Hi devs,
The 3.3 Milestone 2 release was supposed to happen this past Monday, but the codebase hasn't been stable enough for a release (failing tests, hot commits triggering comments, unmerged branches).
Regarding failing tests, we are almost done, but there is now an issue with o.x.t.u.a.UserProfileTest which hangs test-ui. This has happen just after upgrade to Selenium 2.12.0. We need someone to look at it ASAP. Most comments on my recent "hot" commit has been taken into account, and only Vincent seems to be still unhappy. It should be noted that we have progressed and even if the API is still fragile, it is far less then before. It will stay a work in progress anyway for a few release, this is probably unavoidable with such changes.
Proposal 1: Release 3.3 RC 1 next Monday, 21 November, effectively dropping Milestone 2. This respects the initial schedule, although some of the targeted features won't be fully usable. This means that everyone should try to get their code stabilized.
Proposal 2: Lengthen the release by another week, releasing: - Milestone 2 next Monday, November 21 - RC1 on November 28 - Final on December 5
I'm fine with either one, if the codebase is stable enough for a RC by next Monday.
Like you I am fine with both, I would be even be more happy to branch master as soon as possible since I have waiting stuff for 3.4. But if we release RC1 on schedule, does it contains enough for a useful release ?
-- Sergiu Dumitriu http://purl.org/net/sergiu/ ______________________________**_________________ devs mailing list [email protected] http://lists.xwiki.org/**mailman/listinfo/devs<http://lists.xwiki.org/mailman/listinfo/devs>
-- Denis Gervalle SOFTEC sa - CEO eGuilde sarl - CTO
On Thu, Nov 17, 2011 at 8:51 PM, Sergiu Dumitriu <[email protected]> wrote:
Hi devs,
The 3.3 Milestone 2 release was supposed to happen this past Monday, but the codebase hasn't been stable enough for a release (failing tests, hot commits triggering comments, unmerged branches).
Proposal 1: Release 3.3 RC 1 next Monday, 21 November, effectively dropping Milestone 2. This respects the initial schedule, although some of the targeted features won't be fully usable. This means that everyone should try to get their code stabilized.
Proposal 2: Lengthen the release by another week, releasing: - Milestone 2 next Monday, November 21 - RC1 on November 28 - Final on December 5
I'm fine with either one, if the codebase is stable enough for a RC by next Monday.
I'm OK with Proposal 1 and a bit more into Proposal 2, mostly depends how much we value release on schedule compare to extra stability check.
-- Sergiu Dumitriu http://purl.org/net/sergiu/ _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
-- Thomas Mortagne
+1 for 2 considering that I still have work to do on AppWithinMinutes for 3.3 Thanks, Marius On Thu, Nov 17, 2011 at 9:51 PM, Sergiu Dumitriu <[email protected]> wrote:
Hi devs,
The 3.3 Milestone 2 release was supposed to happen this past Monday, but the codebase hasn't been stable enough for a release (failing tests, hot commits triggering comments, unmerged branches).
Proposal 1: Release 3.3 RC 1 next Monday, 21 November, effectively dropping Milestone 2. This respects the initial schedule, although some of the targeted features won't be fully usable. This means that everyone should try to get their code stabilized.
Proposal 2: Lengthen the release by another week, releasing: - Milestone 2 next Monday, November 21 - RC1 on November 28 - Final on December 5
I'm fine with either one, if the codebase is stable enough for a RC by next Monday. -- Sergiu Dumitriu http://purl.org/net/sergiu/ _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
On Nov 17, 2011, at 8:51 PM, Sergiu Dumitriu wrote:
Hi devs,
The 3.3 Milestone 2 release was supposed to happen this past Monday, but the codebase hasn't been stable enough for a release (failing tests, hot commits triggering comments, unmerged branches).
Proposal 1: Release 3.3 RC 1 next Monday, 21 November, effectively dropping Milestone 2. This respects the initial schedule, although some of the targeted features won't be fully usable. This means that everyone should try to get their code stabilized.
Proposal 2: Lengthen the release by another week, releasing: - Milestone 2 next Monday, November 21 - RC1 on November 28 - Final on December 5
+1 for 2 but provided Sergiu is able to commit a first version of the EM UI for 3.3M2. This will also give Marius some time to finalize more the AppWithinMinutes and Thomas time to finish the extension.xwiki.org move to XR (updating xwiki.org being part of this - btw it's important we find out what's wrong before the release since it might mean a stability issue in XE 3.3). Thanks -Vincent
I'm fine with either one, if the codebase is stable enough for a RC by next Monday. -- Sergiu Dumitriu http://purl.org/net/sergiu/
+1 for proposal 2. Thanks, Eduard On Fri, Nov 18, 2011 at 10:16 AM, Vincent Massol <[email protected]> wrote:
On Nov 17, 2011, at 8:51 PM, Sergiu Dumitriu wrote:
Hi devs,
The 3.3 Milestone 2 release was supposed to happen this past Monday, but the codebase hasn't been stable enough for a release (failing tests, hot commits triggering comments, unmerged branches).
Proposal 1: Release 3.3 RC 1 next Monday, 21 November, effectively dropping Milestone 2. This respects the initial schedule, although some of the targeted features won't be fully usable. This means that everyone should try to get their code stabilized.
Proposal 2: Lengthen the release by another week, releasing: - Milestone 2 next Monday, November 21 - RC1 on November 28 - Final on December 5
+1 for 2 but provided Sergiu is able to commit a first version of the EM UI for 3.3M2. This will also give Marius some time to finalize more the AppWithinMinutes and Thomas time to finish the extension.xwiki.org move to XR (updating xwiki.org being part of this - btw it's important we find out what's wrong before the release since it might mean a stability issue in XE 3.3).
Thanks -Vincent
I'm fine with either one, if the codebase is stable enough for a RC by next Monday. -- Sergiu Dumitriu http://purl.org/net/sergiu/
devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
participants (6)
-
Denis Gervalle -
Eduard Moraru -
Marius Dumitru Florea -
Sergiu Dumitriu -
Thomas Mortagne -
Vincent Massol