[xwiki-devs] [PROPOSAL] Release process/dates for 4.1-rc-1
In order to try meet a release date, I would like to use the process as documented here: http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1 Synopsis: June 4th: * send 2 day warning mail, ask if anyone needs to block the release. * branch stable-4.1.x to allow 4.2 development to continue. June 6th: * build staged release. * send out call for testing. * do release on jira with release post-dated to the 11th. June 11th: * release from staging. * publish release. I know this is a tight schedule but realistically we need 2 days for warning/stabilization and 2 (working) days for testing. WDYT? Caleb
On 05/31/2012 12:54 PM, Caleb James DeLisle wrote:
In order to try meet a release date, I would like to use the process as documented here:
http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1
Synopsis:
June 4th: * send 2 day warning mail, ask if anyone needs to block the release. * branch stable-4.1.x to allow 4.2 development to continue.
June 6th: * build staged release. * send out call for testing. * do release on jira with release post-dated to the 11th.
June 11th: * release from staging. * publish release.
I know this is a tight schedule but realistically we need 2 days for warning/stabilization and 2 (working) days for testing.
WDYT?
Caleb
Sounds good. I guess that since we're using a proper staging, the RC could actually be the final 4.1 version. -- Sergiu Dumitriu http://purl.org/net/sergiu/
On Jun 1, 2012, at 4:51 AM, Sergiu Dumitriu wrote:
On 05/31/2012 12:54 PM, Caleb James DeLisle wrote:
In order to try meet a release date, I would like to use the process as documented here:
http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1
Synopsis:
June 4th: * send 2 day warning mail, ask if anyone needs to block the release. * branch stable-4.1.x to allow 4.2 development to continue.
June 6th: * build staged release. * send out call for testing. * do release on jira with release post-dated to the 11th.
June 11th: * release from staging. * publish release.
I know this is a tight schedule but realistically we need 2 days for warning/stabilization and 2 (working) days for testing.
WDYT?
ok for me. What's important is that Marius and Thomas can finish what they have planned for the EM in time.
Caleb
Sounds good. I guess that since we're using a proper staging, the RC could actually be the final 4.1 version.
Almost indeed. ATM we have no way to promote an RC into a final so we'll still need to rebuild with the "4.1" version but without source code changes. Thanks -Vincent
+1 Thanks, Marius On Thu, May 31, 2012 at 7:54 PM, Caleb James DeLisle <[email protected]> wrote:
In order to try meet a release date, I would like to use the process as documented here:
http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1
Synopsis:
June 4th: * send 2 day warning mail, ask if anyone needs to block the release. * branch stable-4.1.x to allow 4.2 development to continue.
June 6th: * build staged release. * send out call for testing. * do release on jira with release post-dated to the 11th.
June 11th: * release from staging. * publish release.
I know this is a tight schedule but realistically we need 2 days for warning/stabilization and 2 (working) days for testing.
WDYT?
Caleb
_______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
Hi Caleb, Sorry I had read this mail too quickly before. I see an issue with what you propose: you're removing 1 week of development. What we had decided in the roadmap was: * RC1 on 11th * Final on 18th I don't really understand what you're trying to achieve with the staging. Is it to replace the notion of RC? So far our staging was 1 week, between the 11th and 18th. Now it seems you wish to replace that one week by staging directly the final on 6th till 11th. Thus loosing 1 week of time. IMO we shouldn't have both staging it's useless and eats up precious dev time. So if we keep the dates decided (I don't see any reason to change them) you should start the staging on 11th. We have 2 choices: 1) Staging the final on 11th and promoting it on the 18th 2) Staging the RC on 11th and releasing, letting users have a go at it and then release final on 18th If we choose option 1) we need to be prepared to restage every time we find a problem. We would also need to amend our current overall process, announcements and all our POMs (since they currently say 4.1-rc-1 AFAIK). I have an important preference for 2) since doing 2 will mean the RC1 release will appear on our download page and be announced on all channels this leading to more testing. If we do 1) are you going to announce it as a release on the download page and such? If not, then it's definitely not as good as 2). So right now I'm 1+ for 2) and -0 (very close to -1) for 1). I'm also -1 to do 2 staging since I don't see the usefulness (please explain so that I understand). Maybe I misunderstood something? Thanks -Vincent On May 31, 2012, at 6:54 PM, Caleb James DeLisle wrote:
In order to try meet a release date, I would like to use the process as documented here:
http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1
Synopsis:
June 4th: * send 2 day warning mail, ask if anyone needs to block the release. * branch stable-4.1.x to allow 4.2 development to continue.
June 6th: * build staged release. * send out call for testing. * do release on jira with release post-dated to the 11th.
June 11th: * release from staging. * publish release.
I know this is a tight schedule but realistically we need 2 days for warning/stabilization and 2 (working) days for testing.
WDYT?
Caleb
_______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
On Jun 8, 2012, at 8:59 AM, Vincent Massol wrote:
Hi Caleb,
Sorry I had read this mail too quickly before.
I see an issue with what you propose: you're removing 1 week of development.
What we had decided in the roadmap was: * RC1 on 11th * Final on 18th
I don't really understand what you're trying to achieve with the staging. Is it to replace the notion of RC?
So far our staging was 1 week, between the 11th and 18th.
Now it seems you wish to replace that one week by staging directly the final on 6th till 11th. Thus loosing 1 week of time.
IMO we shouldn't have both staging it's useless and eats up precious dev time.
So if we keep the dates decided (I don't see any reason to change them) you should start the staging on 11th. We have 2 choices: 1) Staging the final on 11th and promoting it on the 18th 2) Staging the RC on 11th and releasing, letting users have a go at it and then release final on 18th
If we choose option 1) we need to be prepared to restage every time we find a problem. We would also need to amend our current overall process, announcements and all our POMs (since they currently say 4.1-rc-1 AFAIK).
I have an important preference for 2) since doing 2 will mean the RC1 release will appear on our download page and be announced on all channels this leading to more testing.
If we do 1) are you going to announce it as a release on the download page and such? If not, then it's definitely not as good as 2).
So right now I'm 1+ for 2) and -0 (very close to -1) for 1).
I'm also -1 to do 2 staging since I don't see the usefulness (please explain so that I understand).
Maybe I misunderstood something?
Note: What's important for me is that we succeed in *reducing* the time it takes to perform releases. By adding a double staging we increase this time a lot thus reducing the little time we have for developing new stuff/improving/fixing bugs. Thanks -Vincent
Thanks -Vincent
On May 31, 2012, at 6:54 PM, Caleb James DeLisle wrote:
In order to try meet a release date, I would like to use the process as documented here:
http://dev.xwiki.org/xwiki/bin/view/Community/ReleasePlans#H4.1RC1
Synopsis:
June 4th: * send 2 day warning mail, ask if anyone needs to block the release. * branch stable-4.1.x to allow 4.2 development to continue.
June 6th: * build staged release. * send out call for testing. * do release on jira with release post-dated to the 11th.
June 11th: * release from staging. * publish release.
I know this is a tight schedule but realistically we need 2 days for warning/stabilization and 2 (working) days for testing.
WDYT?
Caleb