Hi, I've published the XE 1.4 general roadmap directions on http://www.xwiki.org/xwiki/bin/view/Main/Roadmap In addition here's a proposal for the release dates: * 1.4M1: 28th of March 2008 * 1.4M2: 18th of April 2008 * 1.4RC1: 25th of April 2008 * 1.4RC2: 2nd of May 2008 * 1.5 Final: 6th of May 2008 I'm entering those into JIRA Ok with everyone? Thanks -Vincent
On Mar 18, 2008, at 3:19 PM, Vincent Massol wrote:
Hi,
I've published the XE 1.4 general roadmap directions on http://www.xwiki.org/xwiki/bin/view/Main/Roadmap
In addition here's a proposal for the release dates:
* 1.4M1: 28th of March 2008 * 1.4M2: 18th of April 2008 * 1.4RC1: 25th of April 2008 * 1.4RC2: 2nd of May 2008 * 1.5 Final: 6th of May 2008
that's 1.4 final and not 1.5... -Vincent
I'm entering those into JIRA
Ok with everyone?
Thanks -Vincent
Vincent Massol wrote:
Hi,
I've published the XE 1.4 general roadmap directions on http://www.xwiki.org/xwiki/bin/view/Main/Roadmap
In addition here's a proposal for the release dates:
* 1.4M1: 28th of March 2008 * 1.4M2: 18th of April 2008 * 1.4RC1: 25th of April 2008 * 1.4RC2: 2nd of May 2008 * 1.5 Final: 6th of May 2008
I'm entering those into JIRA
Ok with everyone?
Can we put 2 weeks between M2 and RC1? -- Sergiu Dumitriu http://purl.org/net/sergiu/