Hi, On Tue, Apr 7, 2009 at 11:49 AM, Jean-Vincent Drean <[email protected]>wrote:
On Mon, Apr 6, 2009 at 12:35 PM, Vincent Massol <[email protected]> wrote:
Hi,
* We consider the 2.0 release as a normal release that we release early September: - 2.0 M1: 22 June 2009 - 2.0 M2: 13 July 2009 - 2.0 M3: 3 Aug 2009 - 2.0 RC1: 17 Aug 2009 - 2.0 RC2/Final: 31 Aug 2009
+1
+1 as well.
* We add a new skin
I'm not sure about this:
1/ We've spent more than a year stabilizing toucan and we still have issues on some browsers/OS (namely linux). 2/ We lack resources to work on UI related stuff. 3/ XE 1.0 was albatross, it seems logical to me that our next major release uses toucan.
Don't get me wrong, I'd like that we have a new skin but I think that if we can spend time on skin development this summer we should focus on making toucan better before 2.0 (css cleaning, bug fixing, drop albatross). WDYT ?
Well, the aim is not create a new skin for the sake of it but rather to make the wiki easier to use in the release's timeframe. We could indeed spend that time improving toucan, working on items such as: - Cleaning redundant CSS styles - Reorganizing & improving the action bar - Fixing bugs across platforms - Adding new colors - Improving the .../bin/edit/... & .../bin/inline/... pages - Improving dialog boxes (such as the "this page has been deleted" one) The exact release contents would be decided when discussing the roadmap in June. Would that be ok? Guillaume
JV. _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
-- Guillaume Lerouge Product Manager - XWiki Skype ID : wikibc http://guillaumelerouge.com/