15 Jun
2011
15 Jun
'11
12:10 p.m.
Hi devs, I forgot to propose dates in the Roadmap mail for XE 3.2 so here's a proposal: 3.2M1: 18 July 2011 3.2M2: 15 August 2011 3.2M3: 12 Sep 2011 3.2RC1: 26 Sep 2011 3.2 Final: 10 Oct 2011 Rationale: - 4 week for milestone releases - 2 weeks for RC and Final - 1 more milestone than usual since it's holiday time and most committers will be off at least 2 to 4 weeks during the summer Here's my +1 Thanks -Vincent