On 06/20/2011 12:18 PM, Marius Dumitru Florea wrote:
+1. Who's the release manager?
I volunteer.
Thanks, Marius
On 06/15/2011 03:10 PM, Vincent Massol wrote:
Hi devs,
I forgot to propose dates in the Roadmap mail for XE 3.2 so here's a proposal:
3.2M1: 18 July 2011 3.2M2: 15 August 2011 3.2M3: 12 Sep 2011 3.2RC1: 26 Sep 2011 3.2 Final: 10 Oct 2011
Rationale: - 4 week for milestone releases - 2 weeks for RC and Final - 1 more milestone than usual since it's holiday time and most committers will be off at least 2 to 4 weeks during the summer
Here's my +1
-- Sergiu Dumitriu http://purl.org/net/sergiu/