The 3.4 final release has been delayed almost 3 weeks, for various reasons, so we need to adjust the planning for 3.5. I propose:
3.4Final: 23 January (this Monday, so in 3 days) 3.5RC1: 6 February (2 weeks) 3.5Final: 13 February (1 week)
WDYT?
+1 - only remark that on 4-5 February is FOSDEM and some people may have holidays in that period - but maybe will not impact the release Thanks, Caty
I can be the release manager of 3.5 but we need a release manager for the beginning of the 4.x cycle.
Thanks, Marius _______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs