On Mon, Aug 3, 2009 at 09:31, Vincent Massol<[email protected]> wrote:
Hi,
Today is supposed to be the 2.0M3 release date but since we've had lots of delays on 2.0M2 there's no point in releasing M3 today. I've reviewed some of the important tasks we wanted to do in the 2.0 release and that are not done yet:
- section editing in 2.0 syntax - JV - XAR in 2.0 syntax (at least for some pages) - All - new skin - Guillaume + Laurent + someone to implement it (?) - macro categories (this one was decided late and wasn't planned initially so I don't think it's a blocker but I'm still listing it here) - Asiri - clustering/distributed events - Thomas
If I work only on this I should be able to commit a first complete beta this week and write test and improve it during the RC process.
- captcha - Jerome - watch list bug fixes (+ activity stream refactoring) - JV - new blog UI - Caty - new User profile UI - Caty
Are there any more?
The conclusion is that we're very late. We need to decide what we want to skip. From the list I think we should skip the following since the work hasn't been started on them: - new user profile - activity stream refactoring
We need to know from each person listed above when he can have finished his part ASAP in order to define new dates (and hoping to preserve the final 2.0 release date).
Right now I'd suggest we postpone M3 by one week, i.e. to the 10th of August and move RC1 to 24th of Aug. This would mean a final for the 31st or a RC2 for the 31st and a final for the 7th of Sep.
+1
WDYT?
Thanks -Vincent
_______________________________________________ devs mailing list [email protected] http://lists.xwiki.org/mailman/listinfo/devs
-- Thomas Mortagne