On 03/02/2011 04:28 PM, Marius Dumitru Florea wrote:
Hi again,
It looks like we need a few more days to finish the http://lists.xwiki.org/pipermail/devs/2011-February/021938.html and to integrate the user status feature (Sergiu, what's the status on this?)
I have a working version without many features which I'll commit shortly. Unfortunately, it won't progress much since the activity macro and the activity plugin need to be thoroughly rethinked. They weren't designed to support different types of applications AND respect some privacy concerns.
thus I propose to reschedule the 3.0M3 release for Monday, March 7th. As for the rest of the dates, I'd like to move the 3.0RC by one week and keep the 3.0 final unchanged:
3.0RC1: 21th of March 3.0 Final: 28th of March
WDYT?
+1.
Thanks, Marius
On 02/28/2011 01:16 PM, Marius Dumitru Florea wrote:
Hi devs,
The XE 3.0M3 release was planned for today but I'd like to postpone it to Wednesday, March 2, because there are many selenium tests failing, and, at least for the WYSIWYG editor, fixing them is not easy. I propose to keep the dates for the 3.0 RC and final unchanged:
3.0RC1: 14th of March 3.0 Final: 28th of March
Here's my +1
Thanks, Marius
-- Sergiu Dumitriu http://purl.org/net/sergiu/