On Wed, Apr 2, 2008 at 1:44 PM, Vincent Massol <[email protected]> wrote:
* XE 1.4 M1 - Tomorrow * XE 1.4 M2 - April 24 * XE 1.4 RC1 - May 5 * XE 1.4 RC2 - May 12 * XE 1.4 Final - May 16
Before we finalize let's review what we want to include in 1.4M2:
1) new xmlrpc improvements (Fabio) 2) improved stats performance (ThomasM) 3) Skins extensions (Sergiu) 4) some perf improvements (JV)
Imagine we decided to reduce the 1.4M2 release from 3 weeks to 2 weeks in order to have the same final release date for 1.4. What can be done in 1) through 4) within 2 weeks (10 days) starting today?
And ok for 4) Since everyone is ok to have a 2 weeks long 1.4M2 let's keep the old release dates : * XE 1.4 M1 - today * XE 1.4 M2 - April 18 * XE 1.4 RC1 - April 25 * XE 1.4 RC2 - May 2 * XE 1.4 Final - May 6 If it's ok for everyone I'll update those dates in JIRA today. Thanks, -- Jean-Vincent Drean