25 Apr
2008
25 Apr
'08
8:28 p.m.
We also need new dates for 1.4RC1, RC2 (if needed) and final since we've slipped by a week. I propose: 1.4RC1: 30th of April 1.4RC2 or final: 9th of May WDYT? Thanks -Vincent On Apr 25, 2008, at 9:38 PM, Vincent Massol wrote:
We also need to release the jira projects, create the missing ones (skinx, etc), upload to OW, etc
-Vincent
On Apr 25, 2008, at 8:44 PM, Jean-Vincent Drean wrote:
Release completed on the maven side, I'll make the announcements on monday. Platform core, web and xwiki enterprise are now in version 1.5 in the trunk, branches have been created for 1.4 versions.
Thanks, JV.
On Fri, Apr 25, 2008 at 5:01 PM, Jean-Vincent Drean <[email protected]> wrote:
The build is now stable, starting the release.
Thanks,