+1 (non-binding), as long as we've got enough time left to get a 1.5 out of
the door by the end of august ;-)
.Make sure you include testing on IE6/7 in the task list.
I'll take care of that bit as soon as the M2 becomes available on the Maven
repo in a standalone distribution.
Guillaume
On Jun 3, 2008, at 9:51 AM, Jerome Velociter wrote:
Hello devs,
XWS 1.1 M2 was originally planned for May 26th. Unfortunately, I
have been
taken by other projects and could not stick to that date. I give you
here
a status on what needs to be achieved and new dates proposal.
For me, the consequent tasks left to be done for us to be feature
closed
for M2 are the following:
* XWS-7 (Manage groups of administrators & power users). It has been
started by Florin. For me it's 80% complete today. Florin will
continue to
work on it.
* XWS-79 (Invitation management). About 50% complete.
* XWS-23 Support public registration
As for dates, here is my proposal :
* 1.1 M2 next Monday (June 9th)
* 1.1 RC1 on June 19th
* 1.1 RC2 or 1.1 final on June 30th.
wdyt ?
Regards,
Jerome.