+1
On Thu, Sep 3, 2009 at 2:55 PM, Vincent Massol <vincent(a)massol.net> wrote:
Guys,
Seen that we're now the 3rd of Sep and we're not ready to release the
new colibri skin (lots of remaining issues), I'd like to propose to
postpone the release by 1 week with the new timetable:
* XE 2.0RC1: 10th of Sep
* XE 2.0 final (if no RC2): 15th of Sep
* XE 2.0RC2 (if blockers found in RC1): 17th of Sep
* XE 2.0 final (if RC2): 22nd of Sep
Here's my +1
Thanks
-Vincent
On Thu, Aug 27, 2009 at 11:02 AM, Vincent Massol<vincent(a)massol.net>
wrote:
Hi,
Since we've just released 2.0M4 we need to reschedule the date for the
2.0
release.
I'm proposing:
* 2.0RC1: 2nd of Sep
* If no blocking bug found in RC1:
** 2.0 final: 4th of Sept (it's just a re-release of RC1 in this case)
* If blocking bugs found in RC1:
** 2.0RC2: 9th of Sep
** 2.0 final: 11th of Sep (it's just a re-release of RC2 in this case)
WDYT?
Thanks
-Vincent
_______________________________________________
devs mailing list
devs(a)xwiki.org
http://lists.xwiki.org/mailman/listinfo/devs
_______________________________________________
devs mailing list
devs(a)xwiki.org