I still think we need a bit more time for the first beta. We have 34
solved issues, and 30 planned for beta1. But it's the majority's call.
I'm OK for the rest of the roadmap.
On 5/24/07, Vincent Massol <vincent(a)massol.net> wrote:
Hi commiters,
Following our recent conversation, I'd like us to agree on the 1.1
roadmap. Here's my proposal in term of timing:
* 1.1 B1 - 28th of May
* 1.1 B2 - 18th Of June
* 1.1 B3 - 9th of July
* 1.1 RC1 - 30th of July
* 1.1 RC2 - 20th of August
* 1.1 Final - 3rd of September
Note: This is time-boxed development so the delivery dates don't
change (or as little as possible) but the content may change.
See the other thread for the goals defined for 1.1.
Here's my +1
Thanks
-Vincent