Hi,
Since we have failed the 2.2M1 release date I propose the following new schedule:
Original dates:
* 2.2M1: 28 Dec 2009
* 2.2M2: 18 Jan 2010
* 2.2RC1: 1st Feb 2010
* 2.2 RC2/Finale: 8 Feb 2010
New dates:
* 2.2M1: 11th of Jan (or 12th of Jan since Jean-Vincent is almost ready to include the new
profile UI + new watchlist UI and he may need one day more)
* 2.2M2: 25th of Jan (one week more, i.e. 2 weeks in total - That's ok since we've
almost done all planned stuff in 2.2M1 - see
http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap)
* 2.2RC1: 1st Feb
* 2.2 RC2/Finale: 8 Feb
Here's my +1
Thanks