Hi,
Following our roadmap definition (now on
http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap)
here are some date proposals for XE 2.1:
* 2.1 M1: 26 Oct (that's 4 weeks after the 2.0 release)
* 2.1 M2: 16 Nov
* 2.1 RC1: 30 Nov
* 2.1 Final: 7 Dec
Here's my +1 to commit to this schedule.
Note that I propose a not too long release (2 months and 2 weeks)
since 2.1 is meant to be a stabilization release with not many new
things. The new things should be for 2.2 in 2010.
Thanks
-Vincent
_______________________________________________
devs mailing list
devs(a)xwiki.org
http://lists.xwiki.org/mailman/listinfo/devs