Result: 4 +1 votes, no 0, no -1.
Hence the vote is passed. I have put those in JIRA.
Thanks
-Vincent
On May 26, 2007, at 10:25 AM, Vincent Massol wrote:
Hi,
I'd like to propose changing our naming of releases to use
Milestones instead of betas and alphas.
The main reason is that we're practicing time boxing and agile
development. This means that each release gets new features/
improvements. This is the main point of agile development: release
pieces of working features at each release. Betas suggest that the
release is almost finished in term of features. On Monday we've
planned to release 1.1 Beta 1. However it's no feature complete as
we've planned 3 betas and 2 rcs and we plan to add features in the
betas.
Thus I believe we should use the word "Milestone" which is better
suited for our style of development (Note: Milestone was suggest by
Sergiu, I'm just borrowing his idea here ;-)).
So I'd suggest to change our plan to be:
* 1.1 M1 - 28th of May
* 1.1 M2 - 18th Of June
* 1.1 M3 - 9th of July
* 1.1 M4 - 30th of July
* 1.1 M5 - 20th of August
* 1.1 Final - 3rd of September
We only need to agree that M4 and M5 should be focused on bug
fixing and not introduce new features (or smallish ones only). This
is because we're not yet quite ready with our automated tests. If
we had a strong suite of tests we wouldn't need to do that and this
is the goal we need to achieve. So I hope we'll see more tests
written in M1 to M3.
Here's my +1 to this new name.
Please cast your votes.
Thanks
-Vincent
--
You receive this message as a subscriber of the xwiki-
dev(a)objectweb.org mailing list.
To unsubscribe: mailto:xwiki-dev-unsubscribe@objectweb.org
For general help: mailto:sympa@objectweb.org?subject=help
ObjectWeb mailing lists service home page:
http://www.objectweb.org/
wws