On 01/26/2012 04:49 AM, Marius Dumitru Florea wrote:
Hi devs,
In a previous mail I proposed the following dates for 3.5:
3.5RC1: 6 February (2 weeks)
3.5Final: 13 February (1 week)
As you can see I haven't included a milestone because the initial plan
was to do only bug fixes as 3.5 is the last release of the 3.x cycle.
It seems though that we're going to introduce new stuff and
improvements (for Extension Manager and App Within Minutes at least)
and thus a milestone is now needed. Thus I propose these new dates:
3.5M1: 6 February (2 weeks)
3.5RC1: 13 February (1 week)
3.5Final: 20 February (1 week)
WDYT?
+1
--
Sergiu Dumitriu
http://purl.org/net/sergiu/