On Oct 3, 2008, at 11:46 AM, Vincent Massol wrote:
Hi there,
Today is XE 1.6 release date so let's start planning for XE 1.7.
Here are the dates (to reach a release for Javapolis 2008):
- 1.7M1: 20th of October (that's more than 3 weeks after the 1.6
release)
- 1.7M2: 10th of November (3 weeks after 1.7M1)
- 1.7RC1: 17 Nov (one week after)
- 1.7RC2 or final: 24 Nov (one week after)
- 1.7 final (if needed): 1st of December
Thus it's a short release (2 months).
Proposed content:
* Working and usable (i.e. users can use them for their day to day
work instead of the old Syntax and old WYSIWYG editor) versions of new
rendering and new WYSIWYG editor. (Vincent, Thomas, Marius)
And Jean-Vincent since he'll work on the automated functional tests
framework for the GWT editor + on the improved inline edit feature
that we need for the new rendering too.
* Working JCR (can be used for day to day work instead of Hibernate).
(Artem)
* French XE (Jean-Vincent)
* Blog revamping (Sergiu)
* Webdav integration (Asiri)
And bug fixes of course.
Anything else planned? (I think we should be careful not to over
commit).
I'd like to have Office import too (Wang Ning) but I don't know how
much time he'll get.
Thanks
-Vincent
Note: I've updated
http://enterprise.xwiki.org/xwiki/bin/view/Main/Roadmap
Thanks