I forgot to propose dates in the Roadmap mail for XE 3.2 so here's a proposal:
3.2M1: 18 July 2011
3.2M2: 15 August 2011
3.2M3: 12 Sep 2011
3.2RC1: 26 Sep 2011
3.2 Final: 10 Oct 2011
Rationale:
- 4 week for milestone releases
- 2 weeks for RC and Final
- 1 more milestone than usual since it's holiday time and most committers will be off
at least 2 to 4 weeks during the summer
Here's my +1
Thanks
-Vincent