The 3.3 Milestone 2 release was supposed to happen this past Monday, but the
codebase hasn't been stable enough for a release (failing tests, hot commits
triggering comments, unmerged branches).
Proposal 1: Release 3.3 RC 1 next Monday, 21 November, effectively dropping
Milestone 2. This respects the initial schedule, although some of the
targeted features won't be fully usable. This means that everyone should try
to get their code stabilized.
Proposal 2: Lengthen the release by another week, releasing:
- Milestone 2 next Monday, November 21
- RC1 on November 28
- Final on December 5
I'm fine with either one, if the codebase is stable enough for a RC by next
Monday.
I'm OK with Proposal 1 and a bit more into Proposal 2, mostly depends
how much we value release on schedule compare to extra stability
check.
--
Sergiu Dumitriu
http://purl.org/net/sergiu/
_______________________________________________
devs mailing list
devs(a)xwiki.org
http://lists.xwiki.org/mailman/listinfo/devs
--
Thomas Mortagne